Download Fibox bluEV manual

User browser print dialog to export a PDF file when needed.

Introduction

This chapter goes through basic information of Fibox bluEV charger.

It also explains what tools and preparations are needed before entering the site.

Product specification

Electrical

Output power [kW]1122
No of phases3ph/N/PE
Nominal voltage230V/400V, 50Hz
Nominal current [A]1632
Rated short circuit withstand current, Icw≤ 10 kA / 1 s
Energy meteringMID-certified kWh meter in each outlet
Short circuit protectionMCB for each outlet
MCB for control functions
Residual current protectionType A RCD for each outlet
6 mA DC protection
Input terminals50mm2, daisy chainable
Outlet typeType 2 socket
Number of outlets1-2
Charge typeMode 3
Schuko outlets0/1/2

Communication

Ethernet-port as standard, 4G module as option
Independent load management through Ethernet
OCPP 1.6 interface for remote monitoring and invoicing
RFID-reader and cards for user recognition as option
Status indicator LEDs

Compliance

CertificationSGS
SafetyEN 61851-1
EMCEN 61851-21,
EN 61439-7,
EN 61439-1
ApprovalsCE, UKCA, RoHS

Mechanical enclosure

Environment -25 – + 40 °C
Automatic high ambient temperature de-rating*
IP class54
IK class10
MaterialPolycarbonate
UV classUL746C, f1 (for indoor and outdoor use)
FlammabilityUL94 V0
Halogen-freeHalogen-free, DIN/VDE 0472, Part 815
Product dimensions (w, d, h)360 x 170 x 600 mm
Package dimensions (w, d, h)395 x 680 x 200 mm
Weight [kg]12
MountingWall, pole
ColorRAL 7016 (dark grey, matt)

This charging station is intended to be connected to 3-phase

400 V AC supply network. The station can be used in normal

indoor and outdoor conditions -25 – +40 °C and in locations with nonrestricted

access. The charging station will be mounted

stationary in wall or pedestal and to be used at an altitude up

to 2000 m. This is class I device against electric shock.

Schuko prioritised, max 8 A

Key components

  1. Optional RFID reader
  2. Charging controller
  3. Data cabling interface
  4. Short circuit protection for controller
  5. Power Terminals
  6. LED
  7. Type2 socket
  8. Energy meter
  9. AC residual current protection
  10. Short circuit protection for charging outlets

Dimension drawing

Fibox bluEV dimension drawing
1. Cable inlet in back side and in bottom
2. Wall fastening dimensions
Dimensions of optional pedestal

Needed tools

You might also need:

  1. In case of using thinner than 27 mm power cables, a smaller cable gland is needed
  2. In case of pulling cables from back side, a suitable (eg. rubber) cable gland is required
  3. Wrench for installing pedestal to floor anchor with bolts

Installing USB-C driver

Before configuring Fibox bluEV charging stations for the first time, you need to install proper USB-C drivers to your laptop.

To install USB-C driver, you may need admin rights to your laptop. For this reason it is recommended to install the driver prior to entering the site.

  1. Open downloads folder
  1. Extract / unzip the file to a new folder on your PC
  1. Browse to the folder, where files were unzipped
  2. Install by mouse right click and select “install

Preparing the site

This chapter explains needed preparations in the site before installing Fibox bluEV chargers.

Power cabling

Multiple chargers can be daisy chained together to reduce cable usage.

Power per socket [kW]Nominal output current per socket [A]Minimum cable size (copper / aluminium) [mm2]Recommended maximum cable size [mm2]Terminal size [mm2]
11166 / 163550
223210 / 253550

Always size the feeding power cable respective to its protective fuse size and according to local regulations for electrical installations.

When selecting smaller input fuse than the combined nominal current of multiple chargers, charging outlets can share available current and limit current per outlet.

Installation to pedestal limits maximum cable size.

In pedestal there is one inlet with 60 mm diameter for cabling. Typically you can feed two cables up to 16 mm2 or one cable up to 50 mm2 through this inlet.

Feeding power cabling

Derive and fasten power cables. Do not mount Fibox bluEV chargers yet.

Cabling can be fed from the back or bottom side of the charger.

If you install to a pedestal, cables are always fed from the back side.

When feeding cables from bottom side, ensure enough space for bending rigid power cables.

Preparing power cabling

Prepare wire lengths as shown in below picture. Use ferrules with multi-strand wires.

Data cabling

Standard method of data cabling between Fibox bluEV charging stations is chain connection using ethernet cable. Cable is chained between all chargers behind same feeding fuse/MCB.

Fibox bluEV charging station(s) can operate either

  1. independently in a group
  2. by a 3rd party Charge Point Operator (CPO) system who is monitoring and controlling chargers using OCPP protocol

Remote connection

  1. Independently operating chargers
    • May operate without remote monitoring
    • May be monitored remotely if connected to a router
  2. When used with operator system connecting to operator cloud can be made via
    • Wired connection via ethernet
    • Wireless 4G connection

4G connection is valid for certain Fibox bluEV models and requires SIM card.

Exceptions

When specifically advised by your local Charge Point Operator (CPO), following exceptions may be considered as an option:

  1. a star type data connection to each unit instead of a chain
  2. standalone units each using 4G data connection

Feeding data cabling

Feed ethernet data cabling according to the chosen method.

First Fibox bluEV charger in each chain is here called a “server unit”.

Server unit is used for installer to configure Fibox bluEV chargers in one chain after installation and testing, when

  • installing Fibox bluEV chargers to a new installation
  • adding new Fibox bluEV chargers to an existing installation

Installation to pedestal

Pedestal can be mounted to an existing 60 mm pole or to ground

Installation to ground

  1. Install floor anchor 3469068 to ground and feed cabling through it.
  2. Bolt floor mounting plate 3469048 to floor anchor and feed cabling through it

Bolts to floor anchor are not part of delivery

Installing pedestal

Assemble pedestal around the pole (screws to assemble parts to gether are part of delivery)

Rain cover and info plate on top are delivered separately as options.

Installation to wall

Ensure charger has flat and solid wall available for mounting.

If necessary, drill holes for mounting screws (4 pcs) in advance using the installation template found in the packaging material.

1. Cable inlet in back side and in bottom
2. Wall fastening dimensions

Installation

This chapter goes through installing, mounting and cabling Fibox bluEV chargers.

Make sure the power supply of the feeding power cable to the charging station is disconnected and secured before starting the installation.

Only qualified electricians are allowed to install Fibox bluEV.

Unpacking

Fibox bluEV is packed in recycleable cardboard which contains:

  • Charging station
  • Password label for configuring the charging station
  • Wall fastening profile
  • 2 pcs 50mm cable glands
  • 2 pcs 50mm screw plugs
  • 2 pcs 50mm plastic nut
  • 2 pcs 20mm cable glands
  • 2 pcs 20mm screw plugs
  • 2 pcs 20mm plastic nut
  • 2 pcs rubber screw plugs
  • 2 pcs of service lid keys
  • 2 pcs RFID cards (optional)
  • 4 pan head screws for wall installation

(screws for pedestal installation are delivered together with pedestal)

Opening the covers

  1. Remove service lid using key
  2. Remove front cover using screwdriver

Preparing for cabling from back

  1. Drill opening for cables fed from the back side.
  2. Install suitable cable gasket (not part of delivery)
  3. Close the unnecessary holes in bottom side with screw plugs.

Preparing for cabling from bottom

Install the cable glands to the holes in the bottom.

Close the unnecessary holes in side with screw plugs.

Fibox bluEV comes with openings and glands for Data and Power cabling. Power cable glands are suitable for 27 – 35 mm thick power cabling. In case of using thinner cabling use screw plugs to block the openings and install smaller cable glands (not part of delivery)

Mounting

  1. Mount wall anchor using screws delivered with the product or with the pedestal
  2. Insert Fibox bluEV charger to the wall anchor. In case of installation from the back, pull cabling from the holes made earlier.
  3. Install screws in the bottom corners and cover them with screw plugs

Fix cabling

Pull in cables and tighten cable glands.

To ensure easy and smooth configuration of the units, it is recommended to install all units in chain before continuing to testing and configuration.

Power cabling

It’s recommended to install power cabling with phase rotation between charging stations.

Follow closely the phase orientation in each charger

First Fibox bluEV in chain

Connect incoming/outgoing power cables.

Connect PE wire first then continue to N and to phase wires.

Max torque setting for all screw connections is 10 Nm

Second Fibox bluEV in chain

Connect incoming/outgoing power cables.

Connect PE wire first then continue to N and to phase wires.

Max torque setting for all screw connections is 10 Nm

Notice different phase orientation between first and second charger.

Third Fibox bluEV in chain

Connect incoming/outgoing power cables.

Connect PE wire first then continue to N and to phase wires.

Max torque setting for all screw connections is 10 Nm

Notice different phase orientation between second and third chargers.

All chargers in chain

Continue installing Fibox bluEV chargers. Ensure that their phase orientation follows below guidance.

Data connection

Choose the next step depending of the used data connection type.

Ethernet cabling

Start installing ethernet cabling with the server unit.

  1. Connect optional ethernet cable between router and lower ethernet socket (ETH0) of the first unit.
  2. Mark the server unit
  3. Connect ethernet cable to the upper ethernet socket (ETH1) of the first unit.
  4. Connect the other end to the lower ethernet socket (ETH0) of the second unit.
  5. Repeat steps 3 and 4 between the rest units in the chain.

SIM-card

  1. Insert the SIM card into the slot as far as it will go pressing gently.
  2. Mark the server unit.

Your local Charge Point Operator may have provided you one SIM card or a card per each Fibox bluEV charging station. You can install SIM card to Server units (first of the chain) if they have SIM card slots.

Finishing installation

To ensure easy and smooth configuration of the units, it is recommended to install all units in chain before continuing to testing and configuration.

Testing

Only qualified electricians are allowed to test Fibox bluEV.

Perform electrical testing according to local regulations.

Remember to document results.

It is recommended to perform at least:

  • Ground continuity
  • Insulation resistance
  • Short circuit impedance
  • RCD functionality

Part 1

  1. Make sure all MCB’s and RCD’s are turned off
  2. Perform Ground continuity tests
  3. Turn on RCD’s and 3ph MCB’s
  1. Perform insulation resistance tests
  2. Repeat steps 1-4 with all chargers

Perform electrical testing according to local regulations.

Part 2

  1. Turn on 1ph MCB’s in all chargers under testing.

Perform electrical testing according to local regulations.

Part 4

  1. Perform short circuit impedance tes in each Fibox bluEV charger.
  2. Test RCD’s in each Fibox bluEV charger.

Perform electrical testing according to local regulations.

Part 3

  1. Close covers of each charger.
  1. Turn on power to the units from main supply
  2. Wait for chargers to start up and perform their self-configuration during first start-up.

Perform electrical testing according to local regulations.

Configuration

The server unit has to be configured when installing

  • Fibox bluEV chargers to a new installation
  • new Fibox bluEV chargers to an existing installation

Server unit is the first of each chain.

Configuration of the server unit requires a USB-C driver.

There is live voltage present in the charger when accessing the USB-C port. Configuration is allowed only for qualified electrician using proper personal protective equipment.

Installing USB-C driver

Before configuring Fibox bluEV charging stations for the first time, you need to install proper USB-C drivers to your laptop.

To install USB-C driver, you may need admin rights to your laptop. For this reason it is recommended to install the driver prior to entering the site.

  1. Open downloads folder
  1. Extract / unzip the file to a new folder on your PC
  1. Browse to the folder, where files were unzipped
  2. Install by mouse right click and select “install

Connecting to server unit

  1. Open the service lid of the server unit
  2. Open the cover in middle of the front cover
  3. Connect USB-C cable between the server unit and your laptop

Navigating with internet browser

  1. Open web browser in your laptop
  2. Write address “192.168.5.1” to your internet browser and press enter

Log in

Log in as operator.

 The password is provided in the password label

Overview to web interface

Navigate to Charging Park Charging StationsOverview

Navigation bar is in the left side of the interface.

You should see all installed Fibox bluEV charging stations and their outlets:

  • The topmost charging station (Charging station 1) is the server unit.
  • Charging stations appear in the list respective to their position in the data cabling chain.

Basic settings

  1. Open Charging Park Load Management
  2. Write down the fuse/MCB size feeding the charging stations
  3. Click “Save

Chain of chargers

These steps are required when you have more than one Fibox bluEV charging station in chain.

Enabling load management

  1. Open Load Management
  2. Scroll down to “Charging Points
  3. Make sure “Select all” is ticked.
  4. Click “Save

Phase rotation

Make sure you have installed power cabling with phase rotation correctly.

Phase rotation settings

  1. Open Configuration of first outlet from the top of the list.
  2. Set Connector Phase Rotation according to the below table.
  3. Click “Save changes”.
  4. Repeat steps 1-3 for remaining outlets.

Phase rotation settings table

Position of the chargerConnector phase rotation
1st, 4th, 7th, 10th,... LeftRST - L1 L2 L3
RightTRS - L3 L1 L2
2nd, 5th, 8th, 11th,... LeftTRS - L3 L1 L2
RightSTR - L2 L3 L1
3rd, 6th, 9th, 12th,... LeftSTR - L2 L3 L1
RightRST - L1 L2 L3

RFID cards

  1. Open Charging Park – Whitelist
  2. Press “New entry
  3. Keep a new RFID tag close RFID reader until you hear a beep  
  4. Press “Import
  5. Name the RFID card as the charger serial number and socket side, eg. “123400012 Left
  6. Make sure “Allow charging” is selected.
  7. Change “Expiry date
  8. Press “Save
  9. Repeat steps 2-8 to all RFID cards used in the chain of Fibox bluEV chargers.

Charge Point Operator

These steps are required when setting connection to Charge Point Operators cloud server.

Naming the charging park

  1. Open Charging Park – Load Management
  2. Write location of chargers to “Charging Park Name”. For example address, floor level or physical location in the premises. This helps your Charge Point Operator identify the chargers when monitoring multiple charging stations remotely.
  3. Press “Save

Socket identification

  1. Open the Configuration of the left socket of the first unit from the top.
  2. Name socket it using charging station serial number and position.
  3. Write the physical location of the charger, eg. address and parking lot number.
  4. Click “Save changes”.
  5. Repeat steps 1-4 to the remaining sockets in the list.

This helps your charge point operator identify the individual charging outlet when monitoring multiple charging stations remotely.

User recognition

New Fibox bluEV is set to allow users enable charging depending of model either via:

  • RFID cards
  • Just by plugging the charging cable

Local Charge Point Operator may control user recognition for example via their mobile app. In this case the correct user recognition method has to be set as shown below. If your Charge Point Operator doesn’t provide ways of user arecognition, these settings should not be changed.

  1. Open ”Configuration” of first charger
  2. Change Release Mode to “By OCPP
  3. Insert “OCPP ID”. First socket is always set as 1, the next ones as 2, 3, 4,…
  4. Press “Save Changes”
  5. Repeat steps 1-4 to remaining outlets

OCPP

  1. Open Charging Park OCPP Configuration
  2. In “Network Interface” drop down list, select the used connection type

3. Type the URL you have received from your local Charge Point Operator to “Backend URL” field.

Typical URL: wss://ocpp.Your_Charge_Point_Operator.com:9001/123400012

where 123400012 is a unique ID. It is recommended to use serial number of the server unit as the unique ID.

4. Press “Save”

When connecting Fibox bluEV chargers to backend server for the first time, the connection must be made with unencrypted connection.

4G

  1. Open System Control – Modem
  2. Ensure “Service active” is ticked
  3. Type “SIM Pin” number

Check the SIM PIN number from your local Charge Point Operator or SIM card provider  

  1. APN value” (typical value is “internet”)
  2. Use credentials
  3. Default Route” (typically checked)
  4. Press “Save

Network settings

  1. Open System Control – Network
  2. Check from your local Charge Point Operator the right status for ”No Gateway” field
  3. Press “Save

Finishing configuration

This chapter goes through rebooting the charger, testing that charger configuration is OK, and finishing installation.

Reboot

Reboot the charging station

  1. Open System Control – Status
  2. Press “Reboot system” and confirm selection
  3. Log back in to controller and navigate to System control –  Status
  4. Wait until all fields are in Running status.

Typical waiting time:

Less than 5 minutes in case of a stand-alone unit

Less than 10 minutes in case of multiple chargers in a chain

Test

  1. Open Charging Park OCPP Status
  2. Check that Connection status is green
  3. Inform your local Charge Point Operator that the system is now set up. They should now be able to see the chain on their server.
  4. You may want to test remote connection with your Charge Point Operator before finalizing installation.

Disconnect and close

  1. Disconnect USB-C cable between the server unit and your laptop
  2. Close the cover in middle of the front cover
  3. Close the service lid

Returning loose items

You have now finished installing and commissioning Fibox bluEV chargers.

Deliver the following items to the person responsible for the chargers in premise:

  • Service lid keys
  • Test reports
  • Password labels
  • RFID tags

You can close the guide